Section 74 Delay Damages

Section 74 Delay Damages: Build a Contractual Ceiling and a Separate Reasonable-Compensation Working

Calculate the cap under the delay clause, then assess what can reasonably be recovered under section 74. Verify the breach, any notice required on acceptance, and the evidence of loss.

Reviewed by CA Naveen Saraswat · Chartered Accountant | 5+ years in corporate audit & tax compliance | Ex-Big4

Payroll folder and salary registers

Start with the breached promise, then apply the ceiling

A delay-damages clause does not automatically entitle a customer to collect its full stipulated amount. Under section 74 of the Indian Contract Act, 1872, where there is a breach and a stipulated sum or penalty, any award is limited to reasonable compensation for loss caused by the breach and cannot exceed that sum or penalty. Work out the chargeable delay and contractual limits first; then test the evidence for a reasonable amount. This guide addresses private commercial supply and installation contracts.

Read the applicable text: Indian Contract Act, 1872, sections 55 and 73–74 Supreme Court, Desh Raj v Rohtash Singh, discussion of section 74.

Calculate the contractual claim on the right base

Read the performance milestone, signed changes, grace period, rate and cap together. Some clauses apply only to the value of the delayed portion; others use the whole order. Track any approved extension, periods for which the customer caused delay, acceptance status and whether days or weeks are chargeable. If the contract was voidable for failure to meet an essential deadline and the promisee accepts late performance, check section 55: compensation for that delay may be barred unless the promisee gives notice of its intention to claim it at the time of acceptance. Where concurrency or an alleged extension is disputed, model both positions and preserve the evidence instead of forcing a single date.

Build the compensation case before taking a deduction

The Supreme Court in Desh Raj v Rohtash Singh, Civil Appeal 921 of 2022, discusses section 74, including the ceiling, reasonableness and the treatment of proof where loss is hard to establish. The case concerned earnest money; its section 74 discussion helps frame a delay analysis but does not determine the outcome of a supply dispute. Where actual loss can be proved, collect that evidence. Where loss was caused but is difficult or impossible to quantify, explain why and support any genuine estimate with facts available when the parties agreed the amount. Difficulty proving the amount does not turn a breach causing no loss into a compensable one. A clause described as a genuine pre-estimate is not conclusive simply because of its label.

Reconcile credits and cash security independently

Keep actual loss items, cost savings, substitute performance, earlier settlements and invoice credits on a common incident reference. Net sums already recovered for the same breach from the supported claim to avoid duplication. Track any performance guarantee or retention separately: ability to call a security, entitlement to damages and final settlement depend on the applicable wording and facts. Do not treat withholding from an invoice as proof of legal liability.

Keep scope and exceptions visible

Section 73 distinguishes loss that arises naturally or was in the parties’ contemplation at contracting from remote or indirect loss. It also requires account to be taken of available means of remedying the effects of non-performance. Section 74 adds the stipulated ceiling and reasonable-compensation test. Keep any distinct claim and its cap separate. Section 74 contains an exception for certain bonds involving a public duty or public interest; it is not a general rule for private commercial contracts or for every contract with government.

Six worked illustrations

All facts and amounts are fictional. Calculations illustrate the stated assumptions, not a predetermined legal outcome.

Illustrative example 1: Delayed portion determines the base

Only equipment worth ₹40 lakh out of a ₹120 lakh order is delayed. The clause charges 0.5% of that portion per chargeable week. Three full weeks give ₹60,000 before the cap and reasonableness assessment.

Illustrative example 2: Cap cuts off a long delay

An order worth ₹80 lakh provides 1% per chargeable week subject to 5% of the order. Eight weeks imply ₹6.40 lakh uncapped, but the contractual ceiling is ₹4 lakh.

Illustrative example 3: Signed extension changes the calculation

A daily charge is ₹12,000. Acceptance occurs 18 days after the original date, but a signed variation extends the deadline by seven days; assume no other exclusions. Eleven chargeable days yield ₹1.32 lakh before further tests.

Illustrative example 4: Genuine estimate supported by proxy data

For a line outage, contemporaneous estimates use ₹18,000 per day for 10 expected days plus ₹70,000 for substitute mobilisation. The documented estimate is ₹2.50 lakh. If the stipulated ceiling is ₹2.20 lakh, the supported estimate cannot raise that ceiling.

Illustrative example 5: Prove loss and strip out savings

Assume ₹2.40 lakh substitute cost and ₹0.35 lakh unavoidable extra handling, with ₹0.55 lakh of avoided cost and no duplication. The evidence supports net loss of ₹2.20 lakh; a ₹3 lakh clause ceiling does not establish entitlement to the extra ₹0.80 lakh.

Illustrative example 6: Subtract earlier recovery for the same breach

Assume the parties agree ₹1.80 lakh as reasonable compensation within the ceiling, with a prior ₹0.65 lakh credit expressly for the same delay. The balance is ₹1.15 lakh, before any unrelated invoice reconciliation.

Ten-step verification table

StepActionEvidence
1Identify the signed clause and governing orderAgreement, purchase order and priority terms
2Identify the promised milestoneSpecifications, acceptance and commissioning terms
3Reconcile deadline changesSigned variation log and extensions
4Attribute each delay intervalDaily records, correspondence and dependency chart
5Apply the prescribed base and capContract calculation with independent review
6Collect loss evidenceSubstitute invoices, overtime and savings records
7Support any pre-estimateBid papers, budgets and assumptions at signing
8Check overlap with earlier collectionsCredit notes, retention and recovery ledger
9Review authority to deduct or claimNotice, dispute and set-off provisions
10Record the supported amount and alternativesDated claim memorandum and supporting documents

Sixteen practitioner FAQs

1. Does the clause amount become due automatically?

No. Prove the breach and assess reasonable compensation within the applicable ceiling.

2. Can an adjudicator award more for that stipulated breach?

Section 74 caps reasonable compensation at the named sum or stipulated penalty.

3. Does the description ‘liquidated damages’ settle reasonableness?

No. The drafting label is less informative than the facts supporting the estimate.

4. Is a weekly rate calculated on the whole contract?

Use the agreed base. Do not apply the entire price if the clause specifies only the affected portion.

5. Can I count a partial week as a full week?

Only if the terms support that treatment. Preserve the calendar and clause wording.

6. What if the delivery deadline was extended?

Apply the effective amended deadline, check what any extension expressly reserves and, when section 55 applies, verify notice at the time of accepting late performance.

7. What if the customer delayed site access?

Test causation and the contract's extension or exclusion terms; do not assume the period is chargeable.

8. Can expected loss be used if proving the exact amount is difficult?

A genuine supported estimate can help quantify loss that was caused but is difficult to measure. Explain the loss, the difficulty of proof and the basis for the estimate.

9. What if exact loss is readily documented?

Put the proof in the file instead of relying on the stipulated sum alone.

10. Does a lack of detailed invoices always defeat the claim?

No. Difficulty of proof and the reasonableness of available evidence matter.

11. Can lost revenue and substitute costs both be claimed?

Test overlap and causation. Temporary substitution may have prevented some revenue loss.

12. Does a cap on all liability replace the delay cap?

Read how the provisions interact, including any express exclusions or order of precedence.

13. Does a performance guarantee fix damages?

No. The guarantee and final damages claim need separate analysis.

14. Is a deduction from invoices necessarily authorised?

Review the contract, relevant notices and applicable law before deducting.

15. Can I count an earlier credit as well as collect the full claim?

Reconcile the credit where it compensates the same breach.

16. Does a government counterparty itself trigger the public-duty exception?

No. Section 74 expressly distinguishes a contract with government from undertaking a public duty.

Official sources

Indian Contract Act, 1872, sections 55 and 73–74 Supreme Court, Desh Raj v Rohtash Singh, discussion of section 74